What should we pay attention to during the wiring construction of weak current systems?

What should we pay attention to during the wiring construction of weak current systems?

Wiring construction of horizontal subsystem

The horizontal subsystem completes the function of connecting the information outlet lines from the wiring room to the work area. A light-weight assembled cable tray with hanging items is adopted to provide mechanical protection and support for the horizontal line system.

The assembled trough-shaped cable tray is a closed trough frame installed in the hanging neck, leading from the weak current shaft to each room with information points, and then through the wire tubes of different specifications pre-buried in the wall, the lines are led to the concealed iron box on the wall.

The wiring of the integrated wiring system is star-shaped, with a large amount of cables. According to the standard cable trough design method, the capacity of the cable trough is determined according to the outer diameter of the horizontal line.

That is: the cross-sectional area of ​​the cable trough = the sum of the cross-sectional areas of the horizontal lines * 3

Cable ducts can be selected in different specifications according to the situation. To ensure the turning radius of the cables, the cable ducts must be equipped with branch accessories of corresponding specifications to provide smooth bending of the line routing.

If the exact location of the information outlet cannot be determined, the cable can be coiled around the outlet in the ceiling before pulling the wires. Once the specific location is determined, it can be led to each information outlet.

The horizontal wiring system of Dongguan Exhibition Center adopts Category 6 UTP cables. According to the currently promulgated ANSI/TIA/EIA 568 B-1 Category 6 wiring standard, the following should be noted when laying Category 6 cables:

  • Do not cut the copper core when peeling
  • No sharp bends or knots
  • Avoid stretching the skin
  • The cable cannot be twisted or twisted
  • The bending radius cannot be less than 4 times the outer diameter of the cable

During construction, do not pull the wires hard: the pulling force of a single 4-pair twisted pair is ≤10 kg; the pulling force of two 4-pair twisted pairs is ≤15 kg; the pulling force of multiple 4-pair twisted pairs is ≤40 kg. Do not bundle multiple twisted pairs into one strand, as this will increase crosstalk between pairs.

Six types of system installation precautions:

(1) The total cross-sectional area of ​​the cables placed in the wire tube or wire trough should be 1/3 to 1/2 of the cross-sectional area of ​​the wire tube or wire trough:

  • The filling rate of straight pipes and wire troughs is 1/2
  • The filling rate of curved wire tubes and wire troughs is 1/3

(2) If the pipe groove specifications on site are too small and the wires are filled excessively, performance will be affected.

(3) The bend of the wire tube must be smooth, and the bending radius should be greater than 6 times the outer diameter of the wire tube.

Wiring construction of vertical subsystem

The vertical trunk subsystem is composed of a series of wiring rooms vertically aligned through the shaft. Its wiring design is divided into two parts:

(1) Vertical section of the trunk line

The function of the vertical part is to provide a channel for the vertical dry cable in the weak current well.

This part adopts the reserved cable well method, leaving a rectangular ground hole in the weak current well of each floor for the passage of large-log cables and optical cables for integrated wiring. The cable well is usually located near the wall close to the branch cable, but does not hinder the termination of the distribution frame.

On the wall on the side where the cable well is reserved, a cable climbing frame or cable trough should also be installed. A row of small holes should be opened on the horizontal bars of the climbing frame or cable trough. The large-pair cable is tied on it with a fastening rope for fixing and bearing. If there is a large interference source such as an elevator nearby, a closed metal cable trough should be used to provide shielding protection for the vertical dry cable.

(2) Horizontal channel section of the trunk line:

The function of the horizontal channel part is to provide a passage for the vertical trunk cable from the main equipment room to the weak current shaft on the floor. This part should also adopt a light-weight assembled trough-shaped cable tray with hanging items to place and guide the cables, which can provide mechanical protection for the cables. It also provides a fire-proof seal for the vertical trunk cables. The sturdy space allows the cables to be safely extended to the destination. The material selection algorithm is consistent with the cable trough algorithm of the horizontal subsystem design part. And if a wire tube has two consecutive 90-degree corners, a wire box should be added at one place to prevent the cables from being damaged when pulling the wires.

Like the vertical part, the horizontal channel part must also retain a certain amount of space margin to ensure that new pipelines do not need to be installed when the system is expanded in the future.

Construction technology

(1) Installation of control cabinet foundation steel

Prefabricate the steel sections according to the requirements of the drawings, level and straighten them, and then remove rust; cooperate with the civil construction personnel to place the embedded parts, and then place the steel sections after the foundation strength meets the requirements. At the same time, use a level ruler to align and level. The installation should meet the following requirements:

  • The top of the foundation steel should be 10mm higher than the leveled floor, and the cabinet should be flush with the leveled floor;
  • After burial, use galvanized flat steel-40×4 to weld to the grounding grid at both ends of the foundation steel. After welding, the exposed parts should be treated with anti-corrosion.

Pipeline laying

1. Weak current bridge:

The bridge used in this project will be very common, and it is very convenient to use the cable trough for wiring construction. The cable trough is supported by an angle steel bracket. The angle steel frame is fixed to the bottom of the floor with expansion bolts. It is not necessary to reserve embedded parts on the floor. The cable trough is made of galvanized thin steel plate. When wiring, a certain amount of spare capacity (30%--40%) should be reserved for the cable trough. In the building, in order to meet the requirements of fire prevention, the wires must be put through metal pipes or metal hoses when they come out of the trough, and the wires must not have exposed parts; at the same time, the cable trough should be made of fireproof materials. The construction of the entire pre-buried wire pipe, cable trough and bridge can be composed of several parts: introduction of wiring, auxiliary wiring box or wiring frame; vertical bridge part, floor horizontal pipeline part, niche branch part (including wiring junction box, crossing box, branch box and outlet box and other wiring equipment).

The weak-current bridge is designed comprehensively in the building, and the bridges of many weak-current systems can be shared. The horizontal common bridge of the weak-current system includes the lines of the following systems: UTP cables of the structured wiring system, control lines and video lines of the monitoring system video, video lines of the television system, signal lines of the audio system, etc. Therefore, the common bridge should be properly arranged and separated to avoid mutual signal interference and contradictions. Thin iron plates are used to separate the horizontal weak-current bridge. The size of the bridge is estimated and determined based on the actual amount of wiring, and a variety of specifications are used. In the weak-current shaft, the weak-current system should be equipped with a shaft bridge connected to each floor. The shaft bridge of the weak-current system should be separated separately, and at least divided into three types of bridges: structured wiring, security system and fire protection. The bridge size of each system is determined based on the amount of wiring, and there should be a certain margin to expand the trunk line.

2. Concealed installation of steel pipes:

Pipeline laying must be closely coordinated with civil construction and carried out according to the following process:


Select pipes strictly according to design requirements.

Before installing the pipe, burrs and iron spikes inside the pipe must be removed. Electric welding and flame cutting are strictly prohibited.

During the pipe bending process, attention should be paid to the use of matching pipe benders. There should be no wrinkles, dents and cracks at the bends, and the degree of flattening should not be greater than 10% of the outer diameter of the pipe. When the line is concealed, the bending radius should not be less than 6 times the outer diameter of the pipe. When buried in underground concrete, the bending radius should not be less than 10 times the outer diameter of the pipe; at the same time, the burial depth shall not be less than 30mm. The pipeline should be buried between the two layers of steel bars as much as possible, and overlap should be avoided as much as possible.

When steel pipes are connected by sleeves, the length of the sleeve should be 1.5-3 times the diameter of the pipe, and the pipe mouths must be aligned; when welding is used, the weld should be firm and tight, and the inner surface of the connection should be smooth and flat. The connection of thin-walled steel pipes must be made by threaded connection, and fusion welding is strictly prohibited.

When using sleeves to connect steel pipes embedded in concrete, the joints should be leak-proof to prevent mortar from flowing into and clogging the pipes during pouring.

The connection between the pipe and the box is welded, and the pipe mouth should be 3-5mm higher than the inner wall of the box. Anti-corrosion paint should be applied after welding; the pipe-box connection is fixed with a locking nut, and the pipe thread should be exposed 2-3 turns.

Cooperate closely with civil engineering, carry out construction according to specifications, and seal pipe openings in time to prevent debris from entering and clogging the pipes.

For some pipelines with longer wires and many elbows, iron wire should be threaded in advance to facilitate the threading work in the future.

The connection between pipes and between pipes and boxes should be grounded, and the threaded connection should be bridged with round steel of no less than Φ6 to ensure good grounding.

Pipelines buried underground should avoid passing through equipment foundations as much as possible. When pipelines pass through expansion joints and settlement joints, compensation devices should be installed and flexible grounding jumpers should be made.

Threading and connecting wires in pipes

Threading:

For conductors passing through pipes, the rated voltage should not be lower than 500V; phase wires should be distinguished by color, the colors of phase wires and neutral wires should be different, and PE wires should use yellow and green insulation wires.

Lines of different systems, different voltage levels, and different current categories should not be run in the same pipe or cable tray.

Before threading, use compressed air to clean out the accumulated water and debris in the pipe, and inhale a small amount of talcum powder to reduce friction. Check whether the burrs and cutting edges of the pipe mouth are clean to prevent the insulation of the wire from being damaged during threading.

When paying out the wire, use a wire payout stand to prevent the wire from getting tangled or buckled. At the same time, introduce the wire head into the outer ring of the wire to pay out the wire to avoid messing up the entire reel of wire or making the wire into small circles and tangles.

There should be no joints or kinks in the wires inside the pipe. The joints should be installed in the junction box. The total area of ​​the wires inside the pipe, including the insulation layer, should not be greater than 40% of the empty area inside the pipe. The insulation layer of the wires should not be damaged and the wires should not be twisted.

If there are many wires, in order to prevent the wire ends from being blocked, the wire cores should be stripped out, arranged side by side, wrapped and connected with one end of the lead wire, and then passed through the tube.

When threading the wires, two people should work together. One person pulls the steel wire at one end, and the other person twists all the wires into a bundle at the other end and puts them into the tube. The two people should coordinate their actions and minimize the friction between the wires and the tube.

The quality of the connection of the wires must be guaranteed. When cutting the insulation layer, the wire core must not be damaged. The core wires should be connected tightly and the insulation tape should not be lower than the insulation strength of the original insulation layer.

Please note that the mouth guard should be put on before threading the steel pipe. The construction method of threading first and then putting on the mouth guard is strictly prohibited.

After the wires are connected, the joints should be soldered and wrapped tightly with insulating tape.

Cable laying

Laying of cable protection tube:

  • The cable pipe should not have perforations or cracks, the inner wall should be smooth, the pipe opening should be free of burrs and sharp corners, and the pipe opening should be made into a trumpet shape.
  • After bending the pipe, there should be no cracks, the degree of flattening should not exceed 10%, and the bending radius should not be less than the minimum allowable bending radius of the cable.
  • The outer surface of the cable pipe is painted with asphalt paint for anti-corrosion treatment. The galvanized pipe should be painted with anti-corrosion paint where the galvanized steel is peeling off. Pipes buried in concrete do not need to be painted with anti-corrosion paint.
  • The design requirements for the cable pipe diameter are that the ratio of the inner diameter of the pipe to the outer diameter of the cable should be no less than 1.5. Each cable pipe should not have more than 3 elbows and no more than 2 right-angle bends.
  • The cable protection tube must be grounded, except when the pipe joint is welded by sleeve.
  • The location of the wire conduit leading to the equipment should be convenient for connection to the equipment and should not hinder the disassembly and installation and entry and exit of the equipment.

Installation of control cable duct

Construction procedures:

The quality of cable ducts and accessories must comply with design requirements and current relevant technical standards, and be selected according to the design. The filling rate of cable ducts should not be greater than 40%, and there should be a certain amount of spare space to facilitate future expansion.

The installation of indoor cable ducts is scheduled to be carried out when the basic construction of pipelines and air conditioning is completed.

The surface of the cable duct should be smooth, uniform and dense, the spray coating should be smooth and flat, the weld surface should be uniform and free of cracks.

During installation, close coordination should be made with civil engineering to reserve holes and bury embedded parts. The installation position and height of the cable duct must meet the design requirements and specifications.

The cable duct is laid horizontally with a span of 1.5m. The bracket should be welded firmly, horizontally and vertically. The height deviation of the horizontal bars on the same layer should not be greater than 5mm, and the left and right deviation along the direction of the cable duct should not be greater than 10mm.

Wire duct connections must be bolted, with the nuts on the outside.

When the cable duct uses a lead-out pipe, a hole opener must be used to make the hole. The hole should be neat and consistent with the pipe diameter. It is strictly prohibited to use gas or electric welding to cut the hole. Pipe fittings should be used for connection, and welding is strictly prohibited.

When the straight line of steel cable duct exceeds 30mm, telescopic connecting plates should be used for connection. The turning radius of the cable duct should not be less than the bending radius of the cable.

The cable duct and its supports and hangers should be well grounded. The grounding main line and each section of the cable duct should be reliably connected at least at one point, including elbows. Spring washers should also be installed in places with vibration, and textile copper wires should be used for flexible connections.

Where cable ducts pass through reserved holes, floors, and walls, fireproof partitions and fireproof materials should be used for sealing and isolation to prevent the fire from spreading along the line.

Power supply for weak current system

The power supply and distribution of each weak electronic system equipment should be safe and reliable.

The elements are as follows:

  • Power supply: In addition to the normal power supply, the system equipment must be equipped with a backup power supply.
  • The commonly used electricity should be supplied by two independent power supplies, and if conditions permit, it is best to equip it with an independent power supply.
  • Power supply capacity: spare capacity or reserved space for power transformer and distribution equipment should be reserved to meet the needs of future increase in power equipment and power consumption.
  • Power supply quality: Important system equipment should be equipped with voltage stabilization (or frequency stabilization) devices and UPS power supplies.

The power lines in the vertical shaft should be separated from the structured wiring, security system and fire protection cables.

<<:  Neusoft Yang Jiwen: Cybersecurity companies need to improve their comprehensive capabilities to develop

>>:  What systems does weak current system integration mainly include?

Blog    

Recommend

Even monkeys can penetrate the intranet!

Hello, everyone, I am amazing. I recently turned ...

Will 5G mobile phones and package fees become cheaper and cheaper?

[[350564]] 1China has the largest 5G user group i...

Building a streaming data lake using Flink Hudi

This article introduces how Flink Hudi continuous...

With costs increasing by 30%, will mobile phone prices rise across the board?

This year is the explosive growth period for 5G c...

Interview surprise: What are the common HTTP status codes?

HTTP status code is the response status code retu...

Thoroughly understand cross-domain issues SpringBoot helps you unimpeded

Environment: SpringBoot2.7.16 1. Introduction Cro...

Do you know how to debug Modbus protocol?

[[386743]] The Modbus protocol adopts master-slav...

Behind the surging IPv6, how much do you know about the DHCPv6 protocol?

With the popularization of IPv6 technology, DHCPv...

Smart commercial buildings: Top 10 technologies to watch

In recent years, rapid advances in digital techno...

Correctly understand the wrong ideas in RS-485 wiring process

[[185474]] RS485 bus is widely used in video surv...

With the arrival of 5G, will enterprise-level networks disappear?

Reader Question: Although I am also in the IT ind...